Renovations Improve Building Systems While Maintaining School Operations
CCM oversaw phased renovations to the 291,884 SF Gettysburg Area High School. The $17M project involved a heavy focus on MEP systems, including the replacement of the HVAC system, fire protection system upgrades, and new lighting and control systems. Renovations provided new flooring, restroom modifications, and improvements to the cafeteria. CCM managed the publicly bid, five-prime delivery project and successfully phased the work to keep the school safely open throughout construction. The phasing required intense coordination over two summers to allow key spaces to be fully operational during the school year.